最高学历:
工作年限:
获取测评结果
As a project manager of a large-scale construction project, you think there are more than 500 related parties in the project. Which of the following is the best course of action?
作为一个大型建设项目的项目经理,你认为到项目有500多个可能是相关方。下列做法中,你最好应采取哪一个行动方案?
A. Exclude some interested parties
A. 排除一些相关方
B. Find an effective way to collect the needs of all interested parties
B. 找到一个收集所有相关方需求的有效途径
C. Collect the needs of all the most influential stakeholders
C. 收集所有最具影响力的相关方的需求
D. Contact your manager and ask who is more important
D. 联系你的经理,问哪位更重要