Which of the following is not the cause of the project failure?
以下哪一项不是项目失败的原因?
A.Plans require too many tasks to be done in too short a time
A.计划要求在太短的时间完成太多的任务
B.Poor financial estimates
B.拙劣的财务估算
C.Planning is carried out by a central planning department
C.由一个中心计划编制部门执行计划编制
D.Management lacks experience in project management
D.管理层在项目管理方面缺乏经验